Batlow Water Storage Dam

20,300

Size (m2)

Barolli Orchards

Client

Gundagai NSW

Location

HDPE & Geotextiles

Materials Installed

Enviro Lining

Head Contractor

10 Days

Duration

Enviro Lining was contracted to provide the client with a HDPE lining system that would be fully impermeable. We were never provided any drawings and had to work with an existing dam that had been dug to deep into the rock so unable to contain the leaking. Enviro Lining was able to conduct our own survey of the dam and provide the client with a solution of a Geotextile underlay, with a 2mm HDPE liner.

Enquiries