RECENTLY COMPLETED
MAJOR PROJECTS

Enviro Lining has completed over 35 projects, and we have highlighted a selection of them to showcase the various materials used in the projects as well as the scale as shown in total quantities ranging from 10,000m2 to over 350,000m2.
PROJECT

Bangus Quarry Landfill Cell 1

56,000 | 588

Size (m2) | lm

MH Earthmoving

Client

Gundagai NSW

Location

GCL, HDPE, Geotextiles & Pipe

Materials Installed

MH Earthmoving

Head Contractor

9 Weeks

Duration

The main hurdle with this project was the required turnaround time from the date of award to completion. Enviro Lining was awarded the works in late October, and we were required to finish our works prior to Christmas. We were able to get materials from stock which allowed us to bring our original project timeline in from 18 weeks to just 9 weeks. This 9 week time frame included ordering and delivery of all materials to site, sampling & testing of materials, and the installation & QA on lining system. This meant that our happy client was able to accept waste in the cell by late January.

Enquiries

For any enquiries, questions or commendations, simply click below or call 02 8068 2666