RECENTLY COMPLETED
MAJOR PROJECTS
Bangus Quarry Landfill Cell 1
56,000 | 588
Size (m2) | lm
MH Earthmoving
Client
Gundagai NSW
Location
GCL, HDPE, Geotextiles & Pipe
Materials Installed
MH Earthmoving
Head Contractor
9 Weeks
Duration
The main hurdle with this project was the required turnaround time from the date of award to completion. Enviro Lining was awarded the works in late October, and we were required to finish our works prior to Christmas. We were able to get materials from stock which allowed us to bring our original project timeline in from 18 weeks to just 9 weeks. This 9 week time frame included ordering and delivery of all materials to site, sampling & testing of materials, and the installation & QA on lining system. This meant that our happy client was able to accept waste in the cell by late January.